Planned Release Date

Planned Release Date

It is the date by which an order should be released. When the order to be released is a subcontract order, the supplies should be also provided on the planned release date. In contrast, the date when the order is actually placed is called order release date. When an order is released every time, the planned release date and the order release date is same. But it is common to unify several orders for a certain period and then place them as one order, and thus both dates may be different.

mrp_160.jpg
Related term: Order Release


Reference:JIT Business Research Mr. Hirano Hiroyuki