Single Level Requirements Explosion
It is a function of Requirements Explosion to use the created Schedule Order to refer to Bill of Materials, explore the child item, and then calculate the requirements of each item. In this explosion, working in pairs with another function of Requirements Explosion (that is Sampling), Low Level Code, Level Table, and Activity Chain are used in order to implement a level-by-level explosion. For example, Single Level Requirements Explosion of the order with the quantity of ten in Item A is performed as the figure below shows:
Related term: Requirements Explosion,Extraction
Reference:JIT Business Research Mr. Hirano Hiroyuki
Single Level Pegging | S | Single Level Where-used Bill of Materials